RENSE.COM


The Plum Island Power
Failure - No One Is Talking
From Patricia Doyle, PhD
dr_p_doyle@hotmail.com
1-3-3


Hello, Jeff - I was surprised to see Promed ADMIT that the Plum Island power failure could lead to release of emerging infectious disease pathogens.
 
It is obvious that our "secure?" labs and hospitals will need reliable backup. Maybe now, they can do something.
 
At this point in time, all that terrorists need do is take out power in the areas of secure labs. Our inept backup which means no back up power at all, will do the rest. They would not have to bring in pathogens, as we have them here waiting to escape when the power goes out.
 
Patricia
 
BTW, I do not see the mainstream following up on the Plum Island situation. Where are they. Is Jeff Rense the only media outlet publicizing the dangerous situation at the Plum? Guess so.
 
 
 
POWER LOSS, PLUM ISLAND - USA (NY)
 
A ProMED-mail post ProMED-mail, a program of the International Society for Infectious Diseases http://www.isid.org
 
From: Paul R. Epstein, M.D. paul_epstein@hms.harvard.edu 1-2-02
 
The 3-hour loss of power and the failure of all 3 backup generators at the Plum Island Animal Disease Center in mid-December [2002] do raise fears that the containment of infectious pathogens could have been seriously compromised, and renew concerns about the safety of high-security labs in general. The threat of emerging infectious diseases (unintentional and intentional) raises the importance of reliable back-up power for biomedical institutions.
 
Even optimally maintained back-up diesel generators may fail to cover sustained power outages [such as] occurred at Columbia Presbyterian Medical Center in NYC in the summer of 1999. During the 3-week July heatwave there a blackout occurred in upper Manhattan, and back-up generators successively failed, one after another. Columbia lost biomedical research (tissue cultures, etc.) in 2 buildings. (The story was covered on the front page of the NY Times.) In another incident in a Rhode Island hospital, a patient's death has been attributed to a failure of power and back-up generators. (The case is still in litigation.)
 
Such failures are encouraging several medical schools to install fuel cells for back-up and even primary power generation. In the private sector the Bank of Omaha has already installed a large unit to ensure the continuity of transactions that take place somewhere across the globe, day or night. Fuel cells burn hydrogen (still from natural gas, thus some carbon must be sequestered, as yet) and produce usable hot water (the "cogeneration" boosting efficiency 2-fold at least).
 
Fuel cells provide on-site power, i.e., non-centralized, distributed generation. They are built-in systems that involve redundant pathways and are thus considered 99.99999% reliable.
 
Fuel cells are still expensive. But there are numerous reasons to consider them, that include:
 
1. The vulnerability of diesel back-up systems; 2. The expanding work related to EIDs (emerging infectious diseases of humans, wildlife, and plants); 3. The potential for increased blackouts due to more extreme weather events; 4. The need for clean, non-polluting power sources; and 5. The vulnerability of the electricity grid itself to interruption and attack.
 
Biomedical institutions and those planning for bioterrorism should strongly consider budgeting for and seeking federal financial incentives to install fuel cells as integral to ensuring our safety, security, and health.
 
-- Paul R. Epstein, M.D., M.P.H. Associate Director Center for Health and the Global Environment Harvard Medical School <paul_epstein@hms.harvard.edu>
 
[Disclaimer: ProMED has no financial interest in fuel cells. - Mod.JW]
 
[see also: 2002 ----- Power loss, Plum Island - USA (NY) 20021221.6105] ...............................jw/pg/jw
 
 
Patricia A. Doyle, PhD Please visit my "Emerging Diseases" message board at: http://www.clickitnews.com/emergingdiseases/index.shtml Zhan le Devlesa tai sastimasa Go with God and in Good Health
 
 
 
Comment
 
From Paul Karpf
pkarpf@hps.cc
1-4-3
 
Greetings, Jeff...
Please accept my comments regarding Plum Island and back-up power.  I am the Rental Manager at a Caterpillar Power Systems Dealer in California and I'd like to comment on the proposal to install fuel cells for more reliable back-up power. This premise is flawed because of the following. "Prime Power", standby diesel generators are far more reliable and far more practical than a Hydrogen Fuel Cell.  I don't disagree that Fuel Cells will be better for the environment. I'm only referring to on-site back-up power.
75% of back-up generators that fail to start due so because of improper battery maintenance.  Most of the units that fail after start-up due so because of bad fuel or because the electrical system is old and not tested to full load as prescribed. Hospitals and all critical facilities should start their units every week and run them under full load at least once every 2 years either by preplanning and simulating an actual outage or by using an outside testing company. Fuel tanks must be purged or the fuel "polished" every year. If not, your back-up units will have their fuel filters clogged until all units have shut down. Also, 2 types of diesel generators are sold; "Back-up" and "Prime Power" units. A "Back-up" unit is only designed to provide the specified minimum of power at the lowest possible cost to the customer. These units are just not designed to run for weeks on-end after years of aging. Caterpillar builds Prime Power diesel generators from 100 kilowatts (a kilowatt/kW is 1000 watts) to 2000kW, that, when maintained as we maintain our rental fleet will almost never fail.
 
A critical facility that needs 3 back-up generators should always Spec 4 units. That way you can always take one offline for service or to cover a unit should a problem occur. Most generators will require a complete service after 500 hours of operation. Hospitals in California, by law, must rent Back-up generators when they relay on their on-site generators as their primary source of power, thus they maintain 100% redundancy. In the event of a disaster the County Sheriff already has a plan for us roll immediately to get the local hospitals covered with 100% redundancy. A disaster could easily fill the Emergency and Surgery rooms with critical patients. Another system that should be tested annually is the switch that automatically tells the generators to start and transfers the power to them. This is called an Auto Transfer Switch (ATS). If it fails you won't have power even if the gensets operate properly.
 
 
The Facility Managers for our local hospitals take their generators very seriously. They monitor their battery chargers, water heaters (required for block loading) and fuel systems on a weekly basis. If they don't, the same thing that happened on Plum Island might occur resulting in criminal negligence. Another fine example of proper maintenance is the how many refineries shut-down annually and test every electrical circuit to it's maximum. They do this because a fire or shut-down would result in a huge loss of income.
Some other reasons a fuel cell cannot yet take the place of a back-up diesel generator:
 
We can place a complete 2000KW generator with an underground fuel tank in a 10' x 40' footprint. To my knowledge, a fuel cell of this size would be experimental and require a building of at least 150'x150'. Large hospitals can require anywhere from 4,000 to 10,000kW.
 
A back-up generator at a hospital must start and take the full electrical load within 10 seconds. This is called "Block Loading". Sometimes its an almost violent process that fuel cells are not even close to being capable of handling; at least for now.
 
10,000 gallons of diesel (A truck load) will keep a 2000kW generator running for about 80 hours. How much Hydrogen would it take to equal 10,000 gallons of diesel?
 
Diesel is readily available,  easy to handle, and safe to store. Hydrogen is the complete opposite.
 
A large storage tank of pressurized gas is an easy target to take down.
 
A Fuel cell and all it's components would not survive an earthquake.
 
Maintenance on a Fuel Cell would be far more complex than on a Diesel engine.
 
Fuel Cells have far more things to break on them than a big Diesel engine that was designed to have a run life of 20,000 hours.
So in summary, the generator failures on Plum Island and Columbia Presbyterian were probably caused by a lack of maintenance and testing.
Sincerely,
Paul K.
Rental Manager
San Diego, CA
 
 
Your Comments Are Always Welcome At Rense.com!


Disclaimer





MainPage
http://www.rense.com


This Site Served by TheHostPros